Osisko Development Corp. reported new infill drilling results from its 13,000-meter Lowhee Zone program at the Cariboo Gold Project, with highlights including 596.40 g/t Au over 2.0 meters. Approximately 88% of the planned program is complete, with conclusion anticipated in early Q2 2026 following a temporary suspension due to a prior incident.
Key Takeaways
1Highlight intercept of 596.40 g/t Au over 2.0 meters in drill hole BMU-25-132, including 2,293.56 g/t Au over 0.5 meters.
2Approximately 11,025 meters (~80%) of the planned 13,000-meter infill drilling program completed with full results to date.
3Aggregate drilling totals approximately 12.1 km (~88%) of total planned drill meters completed.
4Infill drilling activities were suspended following an incident reported on January 23, 2026.
5Program is anticipated to conclude in early Q2 2026.