BlockchAIn Digital Infrastructure, Inc. released an investor presentation on April 15, 2026, detailing its power-first AI data center platform, operating footprint, growth pipeline, and financial performance.
Key takeaways
The company's operating footprint includes ~50 MW cash-flowing in South Carolina and a 25 MW site in Minnesota with interconnection in progress.
A growth pipeline targets adding +305 MW by 2027 and +715 MW by 2030 across sites in South Carolina, Texas, and Minnesota.
FY2025 financial results show revenue declined to $18.5M from $22.9M in FY2024, with gross margin falling to 19% from 36%.
The company employs a capital-efficient GP/LP-like development model targeting a ~$9.9B five-year CapEx for its ~715 MW pipeline.
Management attributes the FY2025 revenue decline to lower billing rates, higher energy costs, and the exit of legacy crypto customers.