Eldorado Gold Corporation announced first ore crushed at its Skouries copper-gold project, advancing commissioning toward first concentrate in Q3 2026.
Key takeaways
First ore processed through the crushing circuit at Skouries, a key commissioning milestone.
First production of copper-gold concentrate targeted for Q3 2026; commercial production in Q4 2026.
Ore stockpile of approximately 3.9 million tonnes supports lower-risk commissioning and first year of production.
Final site energization remains subject to Greek power authority inspection and sign-off.
Proactive addition of supplemental gensets to maintain commissioning momentum during power delays.