Prepared Highlights
- Q1 2025 silver production 1,069,000 ounces, a significant increase from Q1 2024 (prepared).
- Open pit ore mined reached ~68% of total ore mined in Q1, versus 70% target split (prepared).
- Stockpile reduced from 300,000 tonnes at start of year to 281,290 tonnes at quarter end (prepared).
- Throughput exceeds nameplate capacity; mill availability in the high 90s (prepared).
- Recoveries at 82% vs. feasibility study target of 89%; issue linked to oxygen plant, now being fixed (CEO).
- Revenue Q1 2025: $33 million; gross profit $10 million; operating income $3.3 million; net income ~$7 million; operating cash flow $7.9 million (prepared).
- Cash and restricted cash post-quarter: ~$37 million; plus $11 million accounts receivable (collected days after quarter end) (CEO).
- EBRD credit facility of $25 million approved and being finalized; total liquidity ~$73 million (CEO).
- Exploration: 46,000 meters drilled at Boumadine in Q1 (program 100,000–140,000 meters); 3,000 meters at Zgounder main structure, 1,000 meters at Zgounder Regional (prepared).
- Boumadine mineral resource update added 100 million silver equivalent ounces (prepared).
- April 2025 production showed continued progress in plant availability, throughput, and mine throughput, with recovery still being worked on (CEO).
- Mx2 spin-out closed with $16 million financing; Aya retains 42% ownership (prepared).
- Drilling costs: $125–160 per meter in Morocco, depending on method and project (CEO).
- EBRD indicated willingness to support Boumadine and other Moroccan initiatives (CEO).
Official guidance (confirmed, same as March 2025):
- Silver production: 5.0–5.3 million ounces for full year 2025, exiting Q4 at 1.5 million ounces per quarter (CEO).
- Cash cost: $15–$17.5 per ounce; AISC adds ~$1–$1.5 (CEO).
- Recoveries: 84–88% (feasibility study target 91%) (CEO).
- Grade: 170–200 g/t globally (CEO).
- Exploration budget: $25–$30 million; 160,000–180,000 meters drilling (CEO).
Mgmt quotes:
- "It's only three months. We know that in our industry, ramp ups can go above one year. Here, we're in the first quarter of the ramp up." (CEO)
- "This is — it's a unique project with tremendous potential." (CEO, on Boumadine)
- "The plant was built on budget. It was commissioned on time." (CEO)
- "Q1 2025 ... a robust quarter in a first quarter ramp up. This is running well above nameplate." (CEO)
- "EBRD is our long term financial partner in Morocco. They support the country. They support Aya." (CEO)
Prepared Metrics
| Metric | Value | Speaker/Context |
|---|
| Silver production | 1,069,000 oz | Q1 2025 (prepared) |
| Open pit ore mined % | ~68% | Q1 average (prepared) |
| Stockpile (end Q1) | 281,290 tonnes | (prepared) |
| Recoveries | 82% | Q1 (CEO) |
| Revenue | $33 million | Q1 2025 (prepared) |
| Gross profit | $10 million | Q1 2025 (prepared) |
| Operating income | $3.3 million | Q1 2025 (prepared) |
| Net income | ~$7 million | Q1 2025 (prepared) |
| Operating cash flow | $7.893 million | Q1 2025 (prepared) |
| Cash & restricted cash (post-quarter) | ~$37 million | (CEO) |
| EBRD credit facility | $25 million | Approved post-quarter (CEO) |
| Boumadine drilling Q1 | 46,000 meters | (prepared) |
| Average realized silver price | $31.87/oz | Q1 2025 (prepared) |
| Cash cost guidance | $15–$17.5/oz | Full year 2025 (CEO) |
| Production guidance | 5.0–5.3 million oz | Full year 2025 (CEO) |
| Exploration program | $25–$30 million; 160k–180k meters | Full year (CEO) |
AYA Q1 2025 Call Q&A Batch (1-4 of 4)
Q1 — Cosmos Chiu
- Topic: Accounts receivable, credit facility, and grade guidance
- Key points:
- $11.6M receivable sold in Q1 but cash received in early Q2; treated as cash.
- $25M EBRD corporate loan approved, documentation to be completed by end of Q2; terms: 2-year bullet, SOFR + 5%, same as construction loan.
- Q1 average grade 163 g/t; April grade dipped. Full-year guidance remains 170–200 g/t. Target: ~200 g/t open pit and ~170 g/t underground by Q4.
- Recovery target 84%–88%; Q1 was 80% due to oxygen plant issues.
- Mgmt stance: Bullish on financial flexibility (loan secured, cash flow improving) and grade improvement (deposit quality confirmed, operational fixes underway).
Q2 — Bryce Adams
- Topic: Cash balance, restricted cash, and open-pit mining costs
- Key points:
- Cash balance as of mid-May is "similar to" end-of-March plus a few million.
- Restricted cash remains restricted until loan maturity (debt service reserve); not available for operations.
- Open-pit contract rates: ~$2/t waste, ~$4/t ore (all-in, including drilling/blasting/hauling). Costs expected to improve with fleet scale.
- Fleet size details not provided on call; mgmt offered to share later.
- Mgmt stance: Neutral on cash (restricted cash clarified as unavailable); bullish on cost improvement from contractor economies of scale.
Q3 — Don DeMarco
- Topic: Throughput, recovery, and free cash flow inflection
- Key points:
- Throughput hit 3,025 t/d in April (above 2,700 t/d nameplate); mgmt expects to sustain ~3,200 t/d. Plant built with 50% expansion capacity (add ball mill + tanks).
- Recovery issue is mechanical (oxygen plant), not metallurgical. No throughput impact from recovery fixes.
- No CapEx for open-pit expansion (contractor-funded). Sustaining CapEx ~$8M this year for underground development.
- Free cash flow already positive in Q1 and expected in Q2.
- Mgmt stance: Bullish on plant performance (robust, overbuilt) and free cash flow generation; neutral on recovery (fixing oxygen plant, no EPC honeymoon).
Q4 — Ovais Habib
- Topic: Cash cost trajectory and underground grade improvement
- Key points:
- Cash costs decreased ~30% QoQ in Q1. Full-year guidance 15%–17.5%. Further step-downs expected in Q2, Q3, Q4 (dependent on grade/recovery denominator).
- Per-ton costs are below budget; cost control is tight.
- Underground improvement: no mining method change. Focus on more definition drilling (reduce dilution, improve grade). Open pit will supply 70% of tonnage to relieve pressure on underground.
- EPC recourse under consideration for oxygen plant delays; mgmt expects compensation in next 1–2 quarters.
- Mgmt stance: Bullish on cost reduction (denominator-driven, per-ton costs good); neutral on underground (requires more drilling discipline); cautious-but-optimistic on EPC recourse (assertive legal stance).